Trade Mark E.A; Offices fit outs for Uganda and Tanzania

The project time period was from May 2010 to December 2010, and the value was USD. 0.5 million.

The project was a design & build office fit out project. With strict cost constraints and timelines. As the project MEP consultants, we engaged local vendors to provide quotes for the various MEP packages and provided on site construction management as well as co-ordination of all MEP trades as well as interface to general contracting works. We developed the designs and have to tightly adhere to overall (pre-determined) construction costs and project programme whilst maintaining the required design standards.